Posted on: June 1, 2018

Valley Street Roadway Improvements

MIlling

The County will start Milling on Monday, June 4th night weather permitting. It will take approximately three nights to mill and then the contractor will reset manholes and repair inlets if any.

After that the road will be paved. The entire duration for milling, resetting / repair inlet / manholes and paving will be approximately 3 - 4 weeks weather permitting.


The limits for milling & paving are Valley St between South Orange Ave to Hixon Place.


It will be a night Job. The contractor, Smith Sondy, has coordinated all the work with South Orange Police and notices will be distributed to the residents today, June 1st and Monday morning.